10037
Barringer Foreman Road |
![]()

Shell, Geismar / Fluor, GOAL/Venture
Substations

This $600,000 project consisted of the construction of two new MCC Substations 24 x 98x 18 eave height and 24 x 86 x 18 eave height, with interior UPS battery rooms. The buildings consisted of a galvanized structural steel frame and metal decking with poured-in-place concrete roof deck. Roofing material was a 3-ply built-up roof system with stainless steel flashing, gutters and downspouts. A total of 25 tons of air conditioning was installed. MOORE self-performed all work except roofing and HVAC. SHELL/FLUOR came to MOORE in the 3rd week of the original 14 week schedule and requested MOORE to dry-in and complete interior finishes to allow MCC equipment installation. MOORE worked 80-90 hours per week and completed the remaining 11 weeks of work in 4 weeks.


Contact us at Moore Construction on how we may assist you in achieving your goals and project needs!